FRIDAY FIELD NOTES #02 Daily Reports Are Project Records Good morning team, This week’s topic: daily reports. From the Field Daily reports can feel routine when the project is moving fast. It is easy to treat them as paperwork that needs to get done at the end of the day so everyone can move on. I’ve learned to look at them differently. A daily report is not just a summary of what happened. It is a project record. It may be used later to explain production, support a change order, confirm manpower, document weather impacts, clarify delays, or reconstruct a project issue after everyone’s memory has faded. The daily report that feels unimportant today may become very important three months from now. Leadership Perspective Good project leaders create good records before there is a problem. Waiting until a dispute, delay, or cost issue appears is usually too late. Documentation is not about mistrust. It is about clarity. Field Observation One pattern I’ve seen is that weak daily reports usually create extra work later. If the report only says “continued demolition” or “worked onsite,” it may technically be filled out, but it does not tell the project story. A stronger daily report explains what area was worked, what crews were onsite, what equipment was used, what changed, what delayed progress, and what was completed. It does not need to be a novel, but it should give enough detail that someone could understand the day without being there. Spreadsheet Tip This week’s formula: TODAY Use this when you want Excel to automatically show the current date. =TODAY() This can be useful in trackers, logs, open item lists, and aging reports. For example, if Column B has the date an item was opened, you can calculate how many days it has been open: =TODAY()-B2 This is useful for RFI logs, submittal logs, change item logs, open action items, and punch list tracking. Question for the Week If someone reviewed yesterday’s daily report three months from now, would they understand what actually happened onsite? Have a great weekend, Dan |
Practical project management lessons from environmental, demolition, remediation, and industrial work. For project engineers, developing PMs, and field professionals. Delivered every Friday.
Good morning team, This week’s topic: small tools and consumables. 1. From the Field Nobody calls an emergency meeting because the project bought another box of cutting wheels. Small purchases rarely look concerning one at a time. Over several months, though, the job may go through far more blades, filters, hoses, batteries, PPE, and other consumables than the estimate allowed. Some small tools will also disappear into gang boxes, service trucks, and whatever mysterious place tape measures go...
Good morning team, This week’s topic: equipment cost exposure. 1. From the Field Equipment costs don’t wait for someone to notice them. A rented excavator can be fueled, inspected, parked in exactly the right spot, and accomplish absolutely nothing while the rental clock keeps running. Sometimes the delay can’t be avoided. An approval may still be pending, the work area might not be ready, or the sequence may have changed. The trouble starts when “we’ll probably need it later” becomes the...
Good morning team, This week’s topic: labor hours. 1. From the Field Knowing that a project used 500 labor hours does not tell you much by itself. You need to know what those hours accomplished. That is where labor tracking becomes more useful. If 500 hours produced 1,000 units one week and the same 500 hours produced 650 the next, something changed. The reason could be completely legitimate, but the project team should understand it. I’ve found that labor discussions become much more useful...